Port of Kamsar, Republic of Guinea continued

     -New layout for railway yard

 

     -Rebuilding of the French Quay used for ships up to 5,000 dwt

 

     -Rehabilitation of drainage for the plant

 

     -Raising and upgrading bucket wheel stacker reclaimers

 

     -Study for replacing elevator building with a ground level wagon tipper

 

     -Study for provision of additional ship loading facilities

 

     -Relocating of conveyor lines including placing in underground tunnels

 

     -New belt cleaning proposals including water saving scheme

 

     -Construction of a new river crossing at the mine

We have been responsible for many improvements, extensions, and rebuilds both at the mine, on the railway, and to the ore reception facilities and general infrastructure in Kamsar: